[ARCHIVED] Traffic Impact Notices, 2021 Improvement Projects and Construction Information

News Flash Icons (17)

Traffic Impact Notices



PROJECT POSTPONED- Work originally scheduled for January 11-15 will take place January 15-21/22.  Weather may continue to affect these dates.


Expect Detours and Delays

January 11 - January 15

Installation of a new sewer main on 80th Ave NW will take place next week, January 11-15.  Flaggers will be in place from 7 AM to 5 PM to direct traffic to the detour. The road will be open when the road crew is not at work.

Jan 2021 Road Closure-Sewer Main

 View Larger



RoadsideMowing

Roadside Maintenance


We would like to remind citizens that periodically, vegetation management takes place along roadsides on public right-of-ways. During the summer, this maintenance increases.

Please note: Inside the city limits, this maintenance is performed by WSDOT, Snohomish County and the City of Stanwood. Any maintenance outside the city limits is performed by WSDOT or Snohomish County. We appreciate the patience and respect shown to our employees and those of the other entities.





2020 City of Stanwood Improvement Projects

The City of Stanwood will be undertaking projects in 2020 that continue its commitment to invest in improvements that make our community safer and enhance our quality of life. While the Stanwood City Council adopts a long-term multiyear capital improvement plan, the projects below are planned for the upcoming year and may be part of a multi-year project that has already started or is starting in 2020. The start and end dates are estimates, as weather may contribute to a delay or extension of the project timeline. Alternate routes are offered for residents, businesses and visitors to consider to lessen the impacts of the construction season. We appreciate your patience as we work!

1. Main Lift Station Upgrades 
Description: Improvements to the main sewer lift station and force main under SR 532.
    Start Date: June 30 End Date: December 31 Alternate Route: 271st Street

2. 276th Repaving and ADA Improvements
Description: Grind and overlay of asphalt from 80th Avenue NW to 73rd Avenue NW. Also includes upgrade of
ADA ramps at various intersections and striping.
    Start Date: July 5 End Date: October 31 Alternate Route: 272nd Street, 284th Street

3. SR 532 & 72nd Ave Intersection Striping
Description: Pedestrian safety project that includes enhanced striping, new signage and an electronic,
illuminated sign that will alert drivers to pedestrians at this wide intersection
    Start Date: June 24, 2019 End Date: August 31, 2020

4. Water Reservoir at 7620 278th Place
Description: Remove an older concrete reservoir and construct a new, 1.5 million gallon steel reservoir. Also
includes a new pad for an emergency generator.
    Start Date: July 31, 2019 End Date: September 30, 2020

5. 90th Avenue NW/Viking Way Improvements
Description: Re-construct 90th Avenue NW from 271st Street to Viking Way and construct Viking Way from the
existing terminus at Petco to 88th Avenue NW. Includes full road, sidewalks, street lights and landscaping.
    Start Date: May 1 End Date: December 31 Alternate Route: 272nd Street

6. SR 532 Flood Berm and Port Susan Trail – Phase I
Description: Construct a flood berm with a paved bicycle/pedestrian path on top. This is a section of the master
loop trail in downtown Stanwood that includes landscaping, benches, art, and hand rail.
    Start Date: March 1 End Date: July 31 Alternate Route: None

7. Irvine Slough Storm Water Separation – Phase 1
Description: Retrofit the existing pump station at the mouth of Irvine Slough to add an additional pump and
separation wall from Irvine Slough. Add piping across Irvine Slough to the North to connect to the existing storm
system from SR 532.
    Start Date: July 31 End Date: December 31 Alternate Route: None

8. Decommission Fure Well and Bryant Well #2
Description: Decommission of 2 wells that have not been used for several years.
    Start Date: July 1 End Date: September 31 Alternate Route: None

Project Map


Facebook Twitter Email

Other News in City News

Mayor, Councilmember and Mother Posing behind Communication Board

City of Stanwood Unveils Communication Board at Church Creek Park

Posted on: February 22, 2024 | Last Modified on: February 8, 2024
Lovers Lane, Image of Culvert Full of Water and Road

Lovers Road Closed for Culvert Repairs

Posted on: February 21, 2024
Snow Geese Flying in Field

Apply for Salary Commission

Posted on: February 21, 2024 | Last Modified on: February 8, 2024
crews working at heritage park

Dog Park Coming Soon

Posted on: February 7, 2024
image of construction tools

Renovations Underway

Posted on: January 23, 2024
Stanwood City Hall

Council Meeting Remarks

Posted on: February 12, 2024
image of stanwood snowplow clearing roads

Winter Weather Updates

Posted on: January 17, 2024
Image of water over road

Flooding Updates

Posted on: January 28, 2024